Charter school building
This property is located on beautiful Father Capodanno Boulevard on the East Shore of Staten Island, New York City – in the Midland Beach neighborhood. Directly adjacent to the Atlantic Ocean (and its Midland Beach), it offers great views of the Verrazzano-Narrows Bridge and Lower New York Bay.
Features:
• A 24,700 sq ft educational facility (charter school) building
• A $9 million project (in 2022 dollars)
• An EB-5 project sponsored by United Land RC LLC (an approved EB-5 Immigrant Investor Regional Center designated by U.S. Citizenship and Immigration Services (USCIS); Regional Center ID – ID1601954225)
• The premises have been leased for a long term to Hebrew Public (a charter schools system) since 2022
• The facility is currently housing a charter school – Staten Island Hebrew Public Charter School
Location (property address):
• 829 Father Capodanno Blvd, Staten Island, NY 10305
Developer: ESL1 Properties LLC
Status: Completed
Completion date: 2022
• Lot 21 (829 Father Capodanno Blvd, Staten Island, NY 10305) | Frontage: 120.61 ft / Depth: 85.53 ft / Area: 9,530 sq ft [#1]
Total Lot Area (1 lot) – 9,530 sq ft
Gross Floor Area – 24,700 sq ft
• R3-2 districts (which are general residence districts that allow a variety of housing types, including low-rise attached houses, small multifamily apartment houses, and detached and semi-detached one- and two-family residences; it is the lowest density zoning district in which multiple dwellings are permitted) – the whole Lot Area
• C1-3 districts (which are commercial overlays mapped within residence districts along streets that serve local retail needs) – the whole Lot Area
Construction work progress – photos
2022 ▼
Part 30 (Finish) - August 2022 - Flower boxes
Part 29 - July 2022 - Railings, flower boxes, inspections
Summer 2022 – July 2022
79 photos
Railings, flower boxes, inspections
View gallery (79 photos - new tab)
Part 28 - June 2022 - Skylights, rooftop flooring, railings
Summer 2022 – June 2022
106 photos
Skylights, rooftop deck flooring, entrance railing
View gallery (106 photos - new tab)
Part 27 - May 2022 - Skylights, painting, cabinets
Part 26 - April 2022 - Sidewalks, flooring, fireproofing
Spring 2022 – April 2022
125 photos
Sidewalks, flooring, fireproofing
View gallery (125 photos - new tab)
Part 25 - March 2022 - Tiling, painting, doors
Part 24 - February 2022 - Cladding, HVAC, elevator, painting
Winter 2021-2022 – February 2022
102 photos
Cladding, HVAC, elevator, painting
View gallery (102 photos - new tab)
Part 23 - January 2022 - Exterior cladding, terrace barriers
Winter 2021-2022 – January 2022
28 photos
Exterior cladding, terrace barriers
View gallery (28 photos - new tab)
2021 ▼
Part 22 - December 2021 - Drywalls, exterior wood cladding
Winter 2021-2022 – December 2021
84 photos
Drywalls, exterior wood cladding
View gallery (84 photos - new tab)
Part 21 - November 2021 - Drywalls, roofing, sidewalks
Fall 2021 – November 2021
125 photos
Drywalls, roofing, sidewalks
View gallery (125 photos - new tab)
Part 20 - October 2021 - Drywalls, roofing, concrete
Part 19 - September 2021 - Drywalls, HVAC
Part 18 - August 2021 - HVAC, waterproofing
Part 17 - July 2021 - Plumbing, HVAC, stucco
Part 16 - June 2021 - Elevator shaft, interior works, plumbing
Summer 2021 – June 2021
21 photos
Elevator shaft, interior works, plumbing
View gallery (21 photos - new tab)
Part 15 - May 2021 - Framing, exterior walls, elevator shaft
Spring 2021 – May 2021
82 photos
Framing, exterior walls, elevator shaft
View gallery (82 photos - new tab)
Part 14 - April 2021 - Structural works, concrete, framing
Spring 2021 – April 2021
114 photos
Structural works, concrete, framing
View gallery (114 photos - new tab)
Part 13 - March 2021 - Structural works, concrete
Part 12 - February 2021 - Structural works, concrete
Winter 2020-2021 – February 2021
70 photos
Structural works, concrete
View gallery (70 photos - new tab)
Part 11 - January 2021 - Structural works
2020 ▼
Part 10 - December 2020 - Sewer, concrete
Part 9 - November 2020 - Earthworks, elevator pit, concrete
Fall 2020 – November 2020
124 photos
Earthworks, elevator pit, concrete
View gallery (124 photos - new tab)
Part 8 - October 2020 - Earthworks, concrete, cellar walls
Fall 2020 – October 2020
122 photos
Earthworks, concrete, cellar walls
View gallery (122 photos - new tab)
Part 7 - September 2020 - Piling, foundation, concrete
Fall 2020 – September 2020
124 photos
Piling, foundation, concrete
View gallery (124 photos - new tab)
Part 6 - August 2020 - Excavation, shoring, piling
Summer 2020 – August 2020
125 photos
Excavation, shoring, piling
View gallery (125 photos - new tab)
Part 5 - July 2020 - Site preparation, excavation
Part 4 - June 2020 - Hand and machine demolition
Part 3 - March 2020 - Fence, preparation for demolition
Spring 2020 – March 2020
25 photos
Fence, preparation for demolition
View gallery (25 photos - new tab)
Part 2 - February 2020 - Fence, pre-demolition surveys
Winter 2019-2020 – February 2020
21 photos
Fence, pre-demolition surveys
View gallery (21 photos - new tab)
Part 1 (Start) - January 2020 - Fence